The U.S. Army Corps of Engineers (USACE) confirmed that the revetment operations at Myrtle Grove were completed on the evening of Saturday, February 5, 2022.
The USACE previously confirmed that the scheduled revetment operations at Kenner Bend were cancelled for this season.
The revetment operations on the Ship Channel have been completed. The FY 2022 sites will be confirmed at a later date and are expected to start in the Fall 2022.
2021/2022 USACE Revetment Schedule and Restrictions Locations Below Baton Rouge
Locations | Mile
(Right or Left) |
2022 Scheduled Dates | Restrictions |
Myrtle Grove |
58.4 RDB |
January 26 to January 28
January 31 to February 7 |
One-way transits with slow bell during working hours. MSU will fold in at night. |
Kenner Bend |
111.3 LDB |
February 9 to February 11
February 14 to February 16 |
One-way transits with slow bell during working hours. MSU will fold in at night. |