The U.S. Army Corps of Engineers (USACE) has confirmed that the revetment operations at Myrtle Grove will not be completed on February 4, 2022, as previously scheduled.  The work at this site is now expected to be completed on Monday, February 7, 2022. 

The updated schedule is reproduced below and shows the new working dates as provided by the USACE.

The expected transit restrictions at Myrtle Grove and Kenner Bend remain one-way transits with a slow bell.

The Mat Sinking Unit (MSU) will operate with scheduled working hours for revetment operations from 0600 hours to 1900 hours. Although, completion is dependent upon multiple factors that could mean work for the day completes before or after 1900 hours.  

2021/2022 USACE Revetment Schedule and Restrictions Locations Below Baton Rouge

 

Locations Mile

(Right or Left)

2022 Scheduled Dates Restrictions
 

Myrtle Grove

 

58.4 RDB

January 26 to January 28  

      January 31 to February 7

One-way transits with slow bell during working hours. MSU will fold in at night. 
 

Kenner Bend

 

111.3 LDB

February 9 to February 11

February 14 to February 16

One-way transits with slow bell during working hours. MSU will fold in at night.