The U.S. Army Corps of Engineers (USACE) continues working on the historic project to deepen the Mississippi River Ship Channel (MRSC) to 50 feet. The USACE has now completed approximately eighty percent (81 %) of Phase 1 of the deepening project. The Phase 1 section of the Ship Channel extends from Venice at Mile 13 Above Head of Passes (AHP) to Mile 22 Below Head of Passes (BHP).  The completion of Phase 1 of the Ship Channel Deepening is expected to open up the first 150-175 miles of the Ship Channel to vessels with deeper drafts. The dustpan dredges HURLEY and WALLACE McGEORGE are expected to begin dredging on the Crossings Above New Orleans in mid-May.  

MISSISSIPPI RIVER SHIP CHANNEL DEEPENING PHASE 1:

The Phase 1 areas of the Ship Channel that could be deepened to 50 feet through the use of cutterhead dredges were completed. The remaining Phase 1 areas will all be deepened by the hopper dredge GLENN EDWARDS (Manson Construction).  The USACE will deepen the Ship Channel from Venice to the Gulf of Mexico (Phase 1) with the three dredge contracts detailed below, specifically the two cutterhead dredge contracts and the one for the hopper dredge GLENN EDWARDS. The USACE expects to complete the deepening project in four progressive upriver phases to the upper end of the MRSC at Mile 233.8 AHP (Baton Rouge).

The details on the cutterhead dredge contracts worked under Phase 1 of the historic river deepening project are detailed below:

Southwest Pass Cutterhead Dredge Rental Contract #1-2020: was awarded to Weeks Marine on August 20, 2020. The cutterhead dredge CAPTAIN FRANK dredged under this contract from September 11, 2020 to March 3, 2021 and the E.W. ELLEFSEN dredged on this deepening contract from November 18, 2020 and completed the last assignment on March 19, 2021.

Southwest Pass Cutterhead Dredge Rental Contract #2-2020: was awarded to Manson Construction on August 27, 2020. The cutterhead dredge ROBERT M. WHITE worked on this contract from October 23, 2020 until completion on March 18, 2021

INDUSTRY HOPPER DREDGES WORKING ON DEEPENING IN SOUTHWEST PASS:

GLENN EDWARDS: The GLENN EDWARDS (Manson Construction) continues working on the Ship Channel deepening project on assignment at the jetty end of SWP from Mile 18.0 BHP to Mile 20.0 BHP.  The cutterhead dredge is working under Southwest Pass Hopper Dredge Rental Contract #9-2020 and will complete the final portions of the Ship Channel deepening project. The hopper dredge is also under contract for Fiscal Year 2021 channel maintenance and will be moved between the two contracts by the MVN dependent upon channel conditions. The GLENN EDWARDS has worked on the deepening project since January 14, 2021.

INDUSTRY HOPPER DREDGES WORKING IN THE AREA OF SOUTHWEST PASS (SWP):

STUYVEASNT: The industry hopper dredge STUYVESANT (Dutra Group) is working on assignment from Mile 10.3 AHP to Mile 9.0 AHP. The STUYVEASNT is working under Southwest Pass Hopper Dredge Rental Contract #6-2020 that was awarded to the Dutra Group in Fiscal Year 2020 to perform channel maintenance in Fiscal Year 2021. The STUYVESANT began work under this contract on March 24, 2021.

NEWPORT: The industry hopper dredge NEWPORT (Manson Construction) is dredging on assignment from Mile 2.4 AHP to Mile 1.4 AHP. The NEWPORT is working under Southwest Pass Hopper Dredge Rental Contract #7-2020 that was awarded to the Manson Construction in Fiscal Year 2020 to perform channel maintenance in Fiscal Year 2021.  The NEWPORT began work under this contract on April 3, 2021.

GOVERNMENT HOPPER DREDGES WORKING IN SOUTHWEST PASS (SWP):

WHEELER: The USACE’s hopper dredge WHEELER is working on assignment in SWP from Mile 11.6 BHP to Mile 15.1 BHP.  The WHEELER began work under Readiness Exercise #1-2021 on
April 25, 2021 and is expected to complete this Readiness Exercise on May 17, 2021.

CUTTERHEAD DREDGE(S) IN THE HOPPER DREDGE DISPOSAL AREA (HDDA):

ILLINOIS: The cutterhead dredge ILLINOIS (Great Lakes Dredge and Dock) has removed and beneficially used approximately 5.0 million cubic yards (mcy) of material from the HDDA under Hopper Dredge Disposal Area Cutterhead Rental Contract #1-2019. The contract includes the removal of 10 mcy in the base with options to add an additional 4 mcy. The project is expected to be completed by early 2022. The material is beneficially being used in the West Bay Receiving Area through a submerged dredge pipeline that will have to be removed up completion of the project. The pipeline retrieval will require at least one complete closure on the Ship Channel in the immediate vicinity of the submerged pipeline (Mile 2.0 AHP to Mile 0 – the Head of Passes).

The Carrollton Gauge (New Orleans) reading at 1000 hours today was 11.49 feet with a 24-hour change of – 0.68 feet.  The latest crest recorded on the Carrollton Gauge was 15.44 feet at 1700 hours on April 16, 2021. The National Oceanic and Atmospheric Administration’s (NOAA) National Weather Service Extended Streamflow Prediction (28-Day) for the Carrollton Gauge issued today forecasts stages to continue a slow fall and then a short rise in about 10 days to 10.6 feet before falling to 7.2 feet on May 28 (2021).

The Baton Rouge Gauge reading at 0900 hours today was 31.60 feet with a 24-hour change of – 0.99 feet. The National Oceanic and Atmospheric Administration’s (NOAA) National Weather Service Extended Streamflow Prediction (28-Day) for the Baton Rouge Gauge issued today predicts stages to continue a slow fall and then a short rise in about 8 days to 28.6 feet before falling to 15.7 feet on May 28 (2021).