The U.S. Army Corps of Engineers (USACE) continues active channel maintenance dredging operations on the Mississippi River Ship Channel (MRSC) in Southwest Pass and previously completed dredging operations on the Crossings Above New Orleans for Fiscal Year 2023 (FY 23).

CUTTERHEAD DREDGE(S) WORKING IN THE HOPPER. DREDGE DISPOSAL AREA (HDDA):

CAPTAIN FRANK: The USACE awarded Head of Passes Hopper Dredge Disposal Area Contract #2-2022 to Weeks Marine to remove sediment from the Hopper Dredge Disposal Area (HDDA). The cutterhead dredge CAPTAIN FRANK continues dredging on assignment in the HDDA and has removed approximately 5.0 million cubic yards (mcy) from the HDDA. Weeks is utilizing the cutterhead dredge CAPTAIN FRANK to remove 6.0 mcy of sediment from the HDDA to be beneficially placed in the West Bay Receiving Area. The submerged dredge pipeline was installed during channel closures in late September, dredging operations started on October 1 (2023). The removed sediment is being beneficially utilized for marsh restoration in the West Bay Receiving Area.

CUTTERHEAD DREDGE(S) WORKING IN SOUTHWEST PASS (SWP):

ALASKA: The cutterhead dredge ALASKA (Great Lakes Dredge & Dock) continues work under Southwest Pass Cutterhead Dredge Contract #1-2023 for channel maintenance dredging in Southwest Pass. The cutterhead dredge is near completion on the present assignment down to Mile 18.0 BHP on the western side of the Ship Channel (right descending bank). The cutterhead is currently located at Mile 17.61 BHP and should complete the present assignment by this weekend. The cutterhead will then move upriver to start a critical assignment to fill a recurring breech near Mile 7.5 BHP along the western side of the Ship Channel, this assignment will extend from Mile 5.0 BHP to Mile 8.0 BHP on the right descending bank. The cutterhead dredge is beneficially utilizing the removed sediment (dredged material) to create new marsh and fortify the banks of Southwest Pass.

MAXIMUM DRAFT RECOMMENDATIONS PER PILOT ASSOCIATION:

(UNCHANGED SINCE July 6, 2023)   

           

The updated maximum draft recommendation for each Pilot Association as adjusted due to the Mississippi River Ship Channel Deepening and a temporary reduction to 49 feet by the Bar Pilots are detailed below:

Associated Branch Pilots of the Port of New Orleans (Bar Pilots): The Bar Pilots returned their maximum draft recommendation to 50 feet (freshwater) on July 6, 2023. The Bar Pilots originally increased their maximum draft recommendation to 50 feet (freshwater) on March 16, 2022, prior to the temporary reduction from May 22 to July 6 (2023).

Crescent River Port Pilots Association (CRPPA): The CPPRA raised their maximum draft recommendation to 50 feet (freshwater) in coordination with the Bar Pilots on July 7, 2023. The CRPPA originally increased their maximum draft to 50 feet (freshwater) on July 20.

New Orleans Baton Rouge Steamship Pilots Association (NOBRA): The NOBRA returned their maximum draft recommendation to 50 feet (freshwater) from Mile 175 AHP to Mile 88 AHP on July 7, 2023. The maximum draft recommendation from Mile 175 to 180 remains 47 feet and from Mile 180 to Mile 233.8 it remains 45 feet.

Associated Federal Pilots and Docking Masters of Louisiana (Federal Pilots): The Federal Pilots increased their maximum draft recommendations to the following to match the draft adjustment to 50 feet by the other Pilot Associations.

 

  1. 50 feet from Sea Buoy to Mile 175 AHP
  2. 45 feet Mile 175 AHP to 232.4 AHP 
  3. 40 feet Mile 232.4 AHP to 233.8 AHP

The controlling maximum freshwater draft for the MRSC from Mile 175 AHP (Smoke Bend) to the Southwest Pass Sea Buoy is 50 feet (freshwater) as adjusted on July 7, 2023.  

Mississippi River Stages and Forecast Updates:

The Carrollton Gage (New Orleans) reading at 1200 hours today was 2.03 feet with a 24-hour change of – 0.52 feet. 

The National Oceanic and Atmospheric Administration’s (NOAA) National Weather Service Extended Streamflow Prediction (28-Day) for the Carrollton Gage issued today forecasts stages will continue a slow rise to 1.7 feet on January 12 and  will then begin a quick fall to 1.4 feet on February 2 (2024).

The Baton Rouge Gage reading at 1200 hours was 6.04 feet with a 24-hour change + 0.24 feet.

The National Oceanic and Atmospheric Administration’s (NOAA) National Weather Service Extended Streamflow Prediction (28-Day) for the Baton Rouge Gauge issued today forecasts stages will begin a quick rise to 9.1 feet on January 11 and will then steadily fall to 4.2 feet on February 2 (2024).