The U.S. Army Corps of Engineers (USACE) has confirmed that the revetment operations at Myrtle Grove are now expected to start at 0600 hours on Wednesday, January 26, 2022. 

The new schedule is reproduced below and shows the updated schedule for the two revetment locations on the Mississippi River Ship Channel.

The expected transit restrictions at Myrtle Grove and Kenner Bend are for one-way transits with a slow bell.

The Big River Coalition’s Corps 2022 Revetment Schedule and Transit Restrictions Update 12022 is attached with the schedule of work as provided by the USACE on January 10, 2022.

(The official schedule has not been adjusted as of this writing.)

The Mat Sinking Unit (MSU) will operate with scheduled working hours for revetment operations from 0600 hours to 1900 hours. Although, completion is dependent upon multiple factors that could mean work for the day completes before or after 1900 hours.  

2021/2022 USACE Revetment Schedule and Restrictions Locations Below Baton Rouge

 

Locations Mile

(Right or Left)

2022 Scheduled Dates Restrictions
 

Myrtle Grove

 

58.4 RDB

January 26 to January 28  

      January 31 to February 5

One-way transits with slow bell during working hours. MSU will fold in at night. 
 

Kenner Bend

 

111.3 LDB

 

February 6 to February 10  

One-way transits with slow bell during working hours. MSU will fold in at night.